Updated
In this guide
The year at a glance
| Season | Months (roughly) | Good for | Watch out for |
|---|---|---|---|
| Post-monsoon and winter | October to February | Foundations, slabs, masonry: the best concreting weather | Cold nights and fog in December and January |
| Spring | March | All work, steady progress | Rising heat towards the end |
| Summer | April to June | Foundations on dry ground, masonry with care | Fast drying, cracks, labour fatigue |
| Monsoon | July to September | Indoor work, plaster and finishing under a roof | Waterlogged pits, damp cement, rust, sand shortages |
Many families start in October or November, get the foundation and first slab done in winter and spring, and have the roof on before the monsoon. That is a good plan if you can manage it.
Winter (October to February): the best time, with cold care
Mild days slow evaporation, so concrete cures well and cracks less. This is the ideal time for footings, columns and slabs.
In December and January, nights can get very cold. Fresh concrete should not be allowed to drop to near freezing, and as a common rule concreting care is needed when it is below about 5°C.
- Pour in the late morning or early afternoon, once the day has warmed, so the concrete sets before night.
- Cover fresh slabs with plastic sheets, hessian or gunny bags overnight.
- Do not use ice-cold water from overnight tanks for mixing on very cold mornings.
- Allow a little more time before removing shuttering, since cold slows strength gain.
- Fog makes surfaces wet but does not replace curing. Keep curing as normal.
Summer (April to June): beat the heat
Try it: Cement calculator
- Cement: 8.1 bags (50 kg)
- Sand: 0.42 m³ (14.8 cu ft)
- Aggregate: 0.84 m³ (29.7 cu ft)
Hot, dry wind pulls water out of fresh concrete and plaster very fast. That causes shrinkage cracks and weaker concrete if you are not careful.
- Pour slabs early in the morning, or in the evening, not in the afternoon sun.
- Keep aggregate in the shade and sprinkle it with water. Use cool water for mixing, and add ice to the mixing water on very hot days if needed.
- Wet the shuttering and the bricks before use so they do not suck water from the mix.
- Start curing as soon as the surface can take it, and keep it continuous: ponding on slabs and wet hessian on columns.
- Cure plaster too, since it cracks easily in summer.
Monsoon (July to September): what can go wrong
The monsoon is a good time for plaster, flooring and finishing work under a completed roof. Avoid starting new foundations if you can.
- Foundation pits fill with water and sides can collapse. Do not cast footings in standing water or on soft, soaked soil.
- Cement absorbs moisture from the air and from damp floors, and forms lumps. Lumpy cement that does not crush between fingers should not be used for structural work.
- TMT bars left on wet ground get rusted. Light surface rust can be brushed off, but flaky, pitted rust is a problem.
- Heavy rain on a fresh slab washes out cement. Cast slabs only on a dry spell, and keep plastic sheets ready.
- Riverbed sand mining is usually restricted during the monsoon, so sand supply tightens and rates can rise.
- Brick kilns generally do not fire in the rains, so red brick supply can also be tight.
Monsoon site checklist
| Item | What to do |
|---|---|
| Cement storage | Store on a raised wooden platform, away from walls, covered with plastic. Use oldest stock first. |
| Steel storage | Keep bars on wooden or brick supports, off the ground, and cover them. |
| Drainage | Make a channel so rainwater runs away from foundations and plinth. |
| Open pits | Pump out water and check sides before work restarts. |
| Slab casting | Check the forecast, cast on a dry day, keep plastic sheets and labour ready. |
| Sand and gitti | Keep stock on a raised, covered spot so it does not wash away or mix with mud. |
| Electrical | Keep temporary site wiring and the mixer's power supply dry and safe. |
| Roof | Finish roof waterproofing and check drain outlets before heavy rain. |
When to book materials
Try it: Steel calculator
Estimated steel: 4,000 kg (4.00 tonnes)
| Bar size | Approx kg | 12 m bars |
|---|---|---|
| 8 mm | 1,000 | 211 |
| 10 mm | 1,000 | 136 |
| 12 mm | 1,000 | 94 |
| 16 mm | 600 | 32 |
| 20 mm | 400 | 14 |
- Stock up on sand and gitti before the monsoon if your work continues through the rains, as supply can be short in July to September.
- Buy cement in lots you will use within a few weeks, not months. Cement loses strength in damp storage, especially in the monsoon.
- Order steel per the bar schedule, a little before each stage. Store it dry.
- Book bricks before the rains when kilns are running. Fly ash bricks and AAC blocks are factory-made and usually less affected by season.
- For winter slabs, plan your steel, cement and gitti a week or two ahead so the casting date is not missed.
- Rates for steel and cement move through the year. WhatsApp or call us for today's rate before placing a large order.
Frequently asked questions
- Which month is best to start building a house in UP?
- October and November are popular, as the monsoon is over and winter gives good concreting weather. Starting then lets you finish the structure before the next rains.
- Can I cast a slab in the monsoon?
- Yes, on a dry spell, with plastic sheets ready in case of rain. Avoid casting during heavy rain, as it washes out cement and weakens the surface.
- Is it safe to pour concrete in winter fog?
- Usually yes in west UP, if you pour after the day warms up and cover the concrete overnight. Take extra care when temperatures drop below about 5°C.
- Why do sand rates go up in the rainy season?
- Riverbed sand mining is usually restricted in the monsoon and transport gets harder, so supply drops. Buying before the rains helps.
- How should I store cement during the rains?
- On a raised platform, away from walls, covered with plastic, and used within a few weeks. Our cement storage guide has the full steps.