Updated
In this guide
First, check the scheme rules that apply to you
There are two main schemes. PMAY-Gramin (PMAY-G) is for rural households, and PMAY-Urban 2.0 is for eligible families in towns and cities. Under the Beneficiary Led Construction (BLC) part of PMAY-U 2.0, you build on your own plot with government help, much like PMAY-G.
At the time of writing, PMAY-G gives about ₹1.2 lakh per house in plain areas, and the house must be at least 25 sq m including a dedicated space for hygienic cooking. PMAY-U 2.0 BLC gives up to about ₹2.5 lakh per house, as combined central and state help, for a house of up to about 45 sq m carpet area. Scheme amounts, sizes and rules can change and may differ by state, so confirm the current figures with your block office (PMAY-G) or your municipal office (PMAY-U).
The scheme money will usually not cover the full cost of the house. Plan the material list for the whole house, then see how much you need to add from savings or a loan.
Rough material quantities for a scheme-sized house
Try it: House construction cost calculator
The cost per sq ft is an editable placeholder for the Standard tier, not a quote. Rates vary by city, brand and labour, so replace it with your contractor's figure.
Total built-up area 1,000 sq ft. Estimated construction cost: ₹18,00,000 at ₹1,800 per sq ft.
Material quantities
- Cement: 420 bags (50 kg)
- Steel: 4,000 kg (4.00 tonnes)
- Sand: 1,300 cu ft (36.8 m³)
- Aggregate: 1,000 cu ft (28.3 m³)
- Bricks: 8,000
The table below is for a single-storey house of roughly 30 to 35 sq m built-up area (about 25 to 30 sq m carpet area): one or two rooms, a kitchen space and a verandah, with 9 inch brick walls and an RCC roof slab. These are planning ranges, not a bill of quantities. Your engineer, or the house design given by the scheme office, sets the real numbers.
| Material | Load-bearing brick walls + RCC slab | Small RCC frame (columns and beams) |
|---|---|---|
| Cement (50 kg bags) | About 110 to 160 bags | About 140 to 190 bags |
| TMT steel | About 400 to 700 kg (slab, lintel band, plinth band) | About 1,200 to 1,700 kg |
| Red bricks (or equal AAC/fly ash blocks) | About 8,000 to 10,000 bricks | About 6,000 to 8,000 bricks |
| Sand | About 15 to 18 cubic metres (roughly 500 to 650 cft) | About 15 to 18 cubic metres |
| Gitti (stone aggregate) | About 7 to 9 cubic metres (roughly 250 to 320 cft) | About 9 to 12 cubic metres |
| Roof | RCC slab about 4 to 5 inch thick over the rooms | RCC slab with beams |
| Doors and windows | 2 to 3 doors, 3 to 4 windows, 1 to 2 ventilators | Same |
Add 3 to 5 percent extra on bricks and sand for breakage and wastage. Put the size of your own house into our calculators for a closer figure, then WhatsApp or call us for today's rate on each item.
Buying plan matched to the instalments
Scheme money is released in instalments as the house reaches set stages. Before each release, the work is usually inspected and geo-tagged photos are taken and uploaded. The exact number of instalments and the stage for each can differ between PMAY-G and PMAY-U and between states, so ask your block or municipal office for your stage list before you start.
Buy materials in lots matched to these stages. That way you never have money locked in material that sits on site for months, and each stage is complete when the inspection comes.
| Stage | What to buy | Tip |
|---|---|---|
| Foundation and plinth | Cement, sand, gitti, bricks for foundation, steel for plinth band, waterproofing for DPC | Finish to plinth level neatly: this is often the first inspection stage |
| Walls up to lintel | Bricks or blocks, cement, sand, steel for lintel band | A continuous lintel band ties the walls together, do not skip it |
| Roof slab | TMT bars, binding wire, cover blocks, cement, sand, gitti, shuttering on hire | Cast the whole slab in one day, then cure it |
| Finishing | Cement and sand for plaster and floor, doors, windows, roof waterproofing | Plaster and floor can be done in parts if funds are short |
Where you can save without cutting safety
- Use Fe500D TMT bars to IS 1786. The D grade bends more before it breaks, which matters in an earthquake. Do not swap to unbranded or re-rolled bars to save money.
- Do not reduce bar sizes or spacing from the drawing. Lower steel is not a saving, it is a risk.
- Cure every pour properly: at least 7 days for OPC and 10 days or more for PPC. Curing costs only water and labour, and it adds real strength.
- Fly ash bricks or AAC blocks can reduce mortar and plaster use. Compare the full wall cost, not only the price per piece.
- Keep the plan simple: a square or rectangular house with walls lined up uses less material than one with many corners.
- Buy steel and cement from one dealer in planned lots and compare rates on the same day. Ask for a bill with brand and grade written on it.
- Store cement off the floor and covered, and keep steel off the ground. Material lost to damp or rust is money lost.
Things that must not be skipped
- Plinth band and lintel band in load-bearing houses. They hold the walls together.
- A damp proof course at plinth level so walls do not soak up ground moisture.
- Cover blocks under the slab bars so the steel stays inside the concrete.
- A proper hygienic cooking space, since it is part of the PMAY-G house requirement.
- Roof waterproofing before the first monsoon.
Frequently asked questions
- How many cement bags are needed for a PM Awas house?
- For a single-storey house of about 30 to 35 sq m built-up with brick walls and an RCC slab, plan for roughly 110 to 160 bags. A column and beam frame needs more. Your actual drawing and wall thickness decide the final count.
- How much steel does a PMAY house need?
- A load-bearing brick house with an RCC slab and bands may need roughly 400 to 700 kg. A small RCC framed house can need 1,200 kg or more. Use Fe500D bars and follow the drawing.
- How much money does PMAY-G give?
- At the time of writing, about ₹1.2 lakh per house in plain areas, released in instalments as construction progresses. Rules and amounts can change, so confirm with your block office.
- Can I buy all the material at once?
- You can, but it is usually better to buy by stage. Money arrives in instalments, and material stored for months on site can be damaged by damp, rain or theft.
- Can Kumar Iron Store help with a PMAY material list?
- Yes. Send us your house size or drawing on WhatsApp and we will help you work out quantities and share today's rates for steel, cement, bricks and blocks.